Project Abstract:
The operational flow of drilling rig construction comprises of several
sub-operations, each with their own set of resource requirements.
With the limited resources in the yard, it is even more imperative
that usage of precious resources such as labor, space, and
operational support tools is utilized to give the optimum output in
terms of high throughput and low cost and lead-time. Three areas
of operations are looked into to improve the usage of these three
resources. In the area of labor loading, effective methods of
manpower forecasting are explored so as to better predict the future
demand of the specialized manpower. For the space operational
improvement, the inventory management of one commonly used
material is studied with the aim of formalizing the replenishment
policy and st¨ZA4e space reduction. Lastly, a set of heuristic is
designed to optimize the inventory level and the usage method of
one operational support resource so as to achieve a lower cost. |